The proposed project, at the City of Helena’s Wastewater Treatment Plant, will replace an existing failed pump station located between the two existing primary clarifiers and the additional underground piping between the pump station and main control building. The pump station is used to transport scum and floatable material from clarifiers at the plant. Replacement of the existing pump will improve treatment and reduce operation and maintenance efforts by plant employees. All work is proposed within the boundaries of the City of Helena Wastewater Treatment Facility.
View Sign
Click Here to View Interactive Project Map.
Doug Compton City of Helena, Civil Engineer (406)447-8073 dcompton@helenamt.gov