Winne #1 and Malben Tank Lining Project

Place CSPE/EIA synthetic liners within the Winne #1 and Malben Storage Tanks. On two potable water tanks on the east side of Helena: Clean, drain, prepare and re-line two existing using synthetic lining material. Re line the Winne #1 Tank, Welded Steel, 600,000 gallons capacity and the Malben Tank, Welded Steel, 4,000,000 gallons capacity.

Estimated Cost: Not yet available

Status: In design

Project Plan Documents (not yet available)

Project Contact:
Jamie Clark, PE
Civil Engineer, City of Helena
Phone: 406-447-8098