Water Reservoir Earthquake Valve Retrofit Project - Complete, December 2016

The project consists of the installation of seismic sensors and new emergency shut off valves at seven reservoir locations. $1,000,000.00 was budgeted for this project in December, 2011.

Project #13-20

Cost Estimate: $782,000.00

Final Cost: $780,723

Status: Bid awarded to Montana Underground Construction, Inc. for $765,761.00 on 11/23/2015 by the Helena City Commission.

Update: Project was completed in August, 2016.